Three separate problems at the wastewater plant: an influent pump needing repair, Blower Number 5's motor burned out, and the UV disinfection system completely down during its summer operating season. The state DNR is aware of the UV problem and wants it fixed quickly.

At a glance

Total mentions
6
Last 30 days
0

Discussed at 1 meeting in the last 60 days; most recently Sep 9, 2026.

Impact analysis

💰Financial impact

Roughly $78,000 in repair and inspection costs if all three items move forward.

✅Who benefits

All residents who rely on the city's wastewater system and clean discharge.

Mentions & discussions (6)

MeetingSep 9, 2026

Common Council - Sep 9, 2026

The council approved a batch of fixes at the wastewater and water plants — a pump, a booster pump, a blower, and a UV disinfection evaluation — totaling roughly $78,000, plus lime slurry hauling.

MeetingAug 26, 2026

Public Works Committee - Aug 26, 2026

Three separate problems at the wastewater plant: an influent pump needing repair, Blower Number 5's motor burned out, and the UV disinfection system completely down during its summer operating season. The state DNR is aware of the UV problem and wants it fixed quickly.

MeetingJul 22, 2026

Public Works Committee - Jul 22, 2026

The city is planning major reinvestment in its wastewater plant. The engineering firm's preliminary report lands in early August, and an intent to apply for federal Clean Water Act money is due in October. The city wants the study widened so every solution is considered before committing.

MeetingJun 10, 2026

Common Council - Jun 10, 2026

The council signed off on the annual state-required wastewater system report, keeping the city compliant with its DNR permit.

MeetingApr 8, 2026

Common Council - Apr 8, 2026

The city locked in up to $550,000 in principal-forgiven loan funding to replace lead water lines from the boulevard to homes, using copper or PEX. Homeowners with lead lines won't repay the principal.

MeetingFeb 11, 2026approved

Common Council - Feb 11, 2026

The city is spending up to $98,000 on a full review of its wastewater treatment plant by Strand & Associates — an early step that could shape future utility investments and rates.

We'll email you when it's on an upcoming agenda and when it's voted on, at most once a day.

The weekly brief for Antigo

What the council decided, in plain English — one email a week.

Free. Unsubscribe with one click any time. We never sell your email.